Samsung SDS begins work on 60 MW AI data center in Gumi
The planned facility will use liquid cooling for high-density GPU server areas, while conventional networking and storage servers will use air cooling. Samsung SDS says the design will accommodate racks with different power requirements, including ultra-high-power configurations. The building is planned at approximately 47,000 square meters, with one underground floor and five above-ground floors, and is designed to serve demand for generative AI and cloud computing. Yonhap reported the design details, including Samsung SDS's plan to install customer-owned equipment.
Samsung SDS said on November 2, 2026, that construction had begun on the 46,000-square-meter site in Gongdan-dong, Gumi, North Gyeongsang Province. Gumi authorities approved construction in late August. The data center will start with 60 megawatts of power capacity and can expand in phases to 120 MW. Completion is targeted for the end of 2028, and full-scale operation is targeted for March 2029.
This is the first project in Samsung Group's 60 trillion won ($44.6 billion) investment plan for the Yeongnam region, announced in July 2026. Samsung SDS approved a 427.3 billion won investment in the project in January and signed an agreement with North Gyeongsang Province and Gumi City. The broader roadmap aims to develop the southeastern region as a global physical AI new idea cluster. It includes humanoid robots and AI data centers in Gumi; all-solid-state batteries in Ulsan; advanced packaging substrates and multilayer ceramic capacitors (MLCCs) for AI servers in Busan; and high-value-added vessels in Geoje, South Gyeongsang Province. Asiae reported that the Gumi center is the first tangible project under the regional investment plan.
Samsung SDS plans to run its own GPU infrastructure while offering colocation services for customers' equipment. The site is intended to serve external customers and Samsung affiliates, including manufacturing robotics initiatives that need computing resources to train AI systems for precision industrial robots.
The design draws on Samsung SDS' 30 years of data center construction and operations experience. It calls for high-capacity power infrastructure and redundant critical systems. Emergency power supplies are also planned to support reliable operation of power-intensive AI servers.
Samsung SDS announced a 427.3 billion won investment in the project and signed a memorandum of understanding with North Gyeongsang Province and Gumi City. CEO Lee June-hee said, "AI is transforming how companies operate and reshaping industrial competitiveness. Turning these changes into tangible results requires a solid foundation capable of processing vast amounts of data and ensuring the stable operation of AI systems."